A COMPARATIVE EVALUATION OF LABOUR PRODUCTIVITY OF FLOOR SCREED ACTIVITY IN SOUTH-SOUTH ZONE OF NIGERIA
1 Department of Building, Faculty of Environmental Studies, University of Uyo, Uyo, Akwa Ibom State, Nigeria
2 Department of Building, Faculty of Environmental Studies, University of Uyo, Uyo, Nigeria
* Corresponding author: isaacodesola@uniuyo.edu.ng
2 Department of Building, Faculty of Environmental Studies, University of Uyo, Uyo, Nigeria
* Corresponding author: isaacodesola@uniuyo.edu.ng
Abstract
Purpose: Improving labour productivity for sustainable practice in a recessed economy cannot
be overemphasised. This study aimed at determining productivity of building craftsmen in floor
screed activity with a view to promoting accurate estimation of manpower requirements for
projects executed in South-South Geo-Political Zone of Nigeria.
Design/methodology/approach: A descriptive survey research design approach was adopted
using continuous observation method in work measurement study. Project work study manual
served as the research instrument to collect data on selected building sites for 30 working days
across six states in the zone. Data collected were analysed using descriptive statistics and
ANOVA.
Findings: The results revealed that there is no significant variation in construction labour
productivity of floor screed activity across the states in the zone. Average construction labour
productivity of floor screed activity in the zone based on a gang comprising an artisan and mate
was 1.90m2/hr. There was also significant variation in nonworking time of construction labour
engaged in floor screed activity in the Zone.
Originality/value: It was concluded that a common productivity norm for floor screed activity
in South-South Geo-Political Zone of Nigeria is feasible and that potentials for productivity
improvement vary across the states in the Zone based on the variation existing in the
nonworking time of construction labour. The study recommended that while common
productivity norm could be adopted for estimating labour resource requirements for floor screed
activity in the Zone cognisance should be made of peculiar business environmental factors in
planning labour productivity improvement strategies.
Keywords
Construction; floor screed; labour; productivity norm; work study
How to Cite
Odesola, I. A., & Ikediashi, D. I. (2017). A COMPARATIVE EVALUATION OF LABOUR PRODUCTIVITY OF FLOOR SCREED ACTIVITY IN SOUTH-SOUTH ZONE OF NIGERIA. Journal of Contemporary Research in the Built Environment, 1(1), 149-162. https://doi.org/10.68128/jocrebe.2017.mra1vwgx
I. A. Odesola, and D. I. Ikediashi, "A COMPARATIVE EVALUATION OF LABOUR PRODUCTIVITY OF FLOOR SCREED ACTIVITY IN SOUTH-SOUTH ZONE OF NIGERIA," Journal of Contemporary Research in the Built Environment, vol. 1, no. 1, pp. 149-162, March 2017. doi: 10.68128/jocrebe.2017.mra1vwgx