CONTRACTORS’ PREQUALIFICATION CRITERIA AND CONSTRUCTION PROJECT COST PERFORMANCE

1 Department of Building, Faculty of Environmental Sciences, University of Lagos, Lagos State, Nigeria
* Corresponding author: john.ameh14@gmail.com
Published: Mar, 2022
Pages: 1-11
Views: 30
Downloads: 11

Abstract

Purpose: Project failure in Nigeria could be linked to poor procedures for selection of contractors, among other causes. This study aimed at examining the impact of Contractor Prequalification Criteria (CPC) on cost performance of construction projects with a view to developing a model for predicting cost performance from prequalification criteria Design/methodology/approach: A well-structured questionnaire was used to gather data from the construction professionals who were registered members of their professional institutions, drawn from contracting, consulting and public client organisations in Ondo State, Nigeria. A sample size of 171 was calculated from the sample frame of 350 using Digeebird statistics sample size calculator at 10% confidence interval and 95% confidence level. Stratified random sampling technique was adopted for the administration of the research instrument. The data were analysed using frequency table and percentage, factor analysis, relative important index (RII), and regression model. Findings: The results indicate a strong relationship between contractors’ prequalification criteria and project cost performance as validated with F value significant at 0.000 Research limitations/implications: It is suggested that more emphasis should be placed on health and safety practices, management capability, organisation reputation, and work experience and capability as they have shown to have impact on cost performance. Originality/value: The study develops a useful model for predicting cost performance from prequalification criteria by construction practitioners and clients.

References

  1. Abdelnaser, O., & Siti, N. B. (2011). Factors affecting cost performance in construction projects within Kelantan state in Malaysia. Journal of Academic Research in Economics, 3(1), 63-76.
  2. Ajayi, M. O. (2010). Multi- criteria decision making model for contractor selection in instruction projects in Nigeria. West Africa built Enviroment Reseach (WABER) (pp. 423-433). Ghana: In Layers, Leirinyer R and Hughes.
  3. Ajayi, M. O., Ogunsanmi, O., & Idoro, G. (2016). Contractor Prequalification Criteria (CPC) and Project Tiime Performance in Nigeria. Lagos Journal of Enviromental Studies, 8(1), 24-34.
  4. Aje, I. (2012). The impact of contractors' prequalification on project delivery in Nigeria. Engineering, Construction and Architectural Management, 19(2), 159-172.
  5. Alarcan, L. F., & Morgues, C. (2002). Performance modeling for contractors' selection. Construction Management in Engineering, 18, 50-62.
  6. Capenter, J. S. (2006). Managing safety risk through whole-life cycle competency. Civil Engineering, 159(2), 57-61.
  7. Chan, A. P., & Tam, C. M. (2000). Factors affecting the quality of building projects in Hong Kong. International Journal of Quality Management, 17(4), 423-441.
  8. Digeebird Statistic Sample Size Calculator. (1982). The Survey System. Retrieved from Creative Research Systems: http://www.surveysystem.com/sscalc.htm
  9. Eady N, S (2007). Contractor prequalififcation program. OLR Research Report 2007-R-0596, Administrative, bridges, construction industries, contracts, Government purchasing, highways, transportation department.
  10. Field, A. (2009). Discovering statistics using SPSS. London: Sage Publication Ltd.
  11. Gransberg, D. D., & Riemer, C. (2009). Performance based construction contractor prequalification: A Synthesis of light way practice transportationresearch board of the national academy. Retrieved January 4, 2019, from www.national-academic.org
  12. Hatush, Z., & Skimore, M. (1997). Assessment and evaluation of contractor data against client goals using pert approach. Construction Management and Economics, 15(5), 327-340.
  13. Jerome, E. S. (2005). Improving Contractor Safety Performance. Retrieved January 9, 2019, from Safety: www.jspear.com
  14. Jin, R., Han, S., Hyun, C., & Cha, Y. (2016). Application of Cased-Based Reasoning for Estimating Preliminary Duration of Building Projects. Journal of Construction Engineering Management, 142(2), 1-8.
  15. Oke, A. E., & Aje, I. O. (2012). An Evaluation of Contractors' prequalification Requirement in Nigeria. Journal of the Nigerian Institute of Quantity Surveyor, 1(1), 1-16.
  16. Olatunji, O. A. (2007). Evaluating the efficiency of prequalification as a tool in comparatives equation in Construction Developing countries. Proceedimg of 2007 Quantity Surveyors, International Convention, (pp. 132-141). Kuala Lumpur, Malaysia.
  17. Proverbs, B., Oloke, D., & Heasom, B. (2007). A knowlwdge based decision supprot system for health and safety competence assessment. In A. o. management (Ed.), 32rd Annual ARCORN Confernrence. 1, p. 307. Belfast, UK: Boyd D Ed press.
  18. Salter, A., & Torbett, R. (2003). Innovation and performance in engineering design. Journal of Construction Management and Economics, 21(6), 573-580.
  19. Victor, K. A., Ernest, K., & Theophilus, A.-K. (2019, April). Ascertaining the impact of contractors prequalification on project success criteria. Engineering Construction and Architectural Management, 1-17.
How to Cite

Ameh, J. O., & Kayode, I. O. (2022). CONTRACTORS’ PREQUALIFICATION CRITERIA AND CONSTRUCTION PROJECT COST PERFORMANCE. Journal of Contemporary Research in the Built Environment, 6(1), 1-11. https://doi.org/10.68128/jocrebe.2022.a0cbfuhr

J. O. Ameh, and I. O. Kayode, "CONTRACTORS’ PREQUALIFICATION CRITERIA AND CONSTRUCTION PROJECT COST PERFORMANCE," Journal of Contemporary Research in the Built Environment, vol. 6, no. 1, pp. 1-11, March 2022. doi: 10.68128/jocrebe.2022.a0cbfuhr

Share this article:
Facebook X / Twitter LinkedIn