EFFECTS OF DELAY ON COST PERFORMANCE OF ROAD CONSTRUCTION PROJECT: CASE OF NIGER DELTA DEVELOPMENT COMMISSION PROJECTS IN NIGERIA
1 Department of Quantity Surveying, School of Environmental Studies, AKS Polytechnic, Ikot Osurua, Nigeria
2 Department of Quantity Surveying, Faculty of Environmental Design and Management, Obafemi Awolowo University, Ile-Ife, Nigeria
3 Department of Building, University of Uyo, Uyo, Akwa Ibom State, Nigeria
* Corresponding author: king13dan2013@gmail.com
2 Department of Quantity Surveying, Faculty of Environmental Design and Management, Obafemi Awolowo University, Ile-Ife, Nigeria
3 Department of Building, University of Uyo, Uyo, Akwa Ibom State, Nigeria
* Corresponding author: king13dan2013@gmail.com
Abstract
Purpose: The reduced cost performance of the Niger Delta Development Commission (NDDC)
road construction projects was caused by construction delay. It makes it essential to evaluate
the effects of road construction delay on cost performance and developed a model for predicting
the cost performance of road projects in the Niger Delta region, Nigeria. Design/methodology/approach: Both primary and secondary data were used for the study and
were analysed using a descriptive method, multiple regression analysis, and Kruskal Wallis H
test for the hypothesis. Secondary data were obtained from initial and final costs and durations
of 136 road projects procured between 2008 and 2018. Findings: Based on the 138 copies of questionnaires retrieved involving registered
professionals in the six selected States, the results showed that the significant effects of delay
on cost performance are: inflation of currency/exchange rates, corruption, total abandonment,
under-development, and dispute and claims/bad reputation. However, the test revealed a
significant variation between Delta and Cross River States and between Edo and Cross River
States. The source of variation might be attributed to frequent patronage of the same contractors
and consultants, high rate inflation and fraudulent/corrupt practices in the procurement and
execution of the projects. Research limitation/implications: The squared coefficient of correlation (R2) value of the
relationship between delay and cost performance is 0.237, revealing that 23.7% of the variation
in the cost performance of road projects can be explained by the delay. It explained the
percentage of delays in the completion of the road project executed by NDDC. Practical implication: The studied variables that contributed significantly to the effect of delay
on the cost performance of road projects procured by NDDC in the study area are nonspecific.
Dereliction of such factors can rob both the client and beneficiaries of the economic benefits of
such development and may aggravate the recurrent agitations and militancy in the region.Originality/value: The identified challenges by this study and their effects could be reduced
through the application of the developed model in the execution of road projects in the region
by the professionals and stakeholders employed by the commission. Participants in the
construction industry in the region, and the world at large, can as well benefit from the
application of the model for road projects with similar attributes, thus improving cost
performance of projects delivery.
Keywords
Cost performance; delay; effect; NDDC
Niger Delta region; road construction project.
References
- Alhomidan, A. (2013). Factors Affecting Cost Overrun in Road Construction Projects in Saudi Arabia. International Journal of Civil & Environmental Engineering (IJCEE-IJENS), 13(3), 1-4.
- Aboubaker, Y. Y, Alfakhri, A. I., and Muhamad, A. K. (2018) The Effects of Delays in Road Construction Projects in Tripoli, Libya. International Journal of Technology 9(4), 167- 175. https://doi.org/10.14716/IJTECH.V9I4.2219
- Abisuga, A. O., Amusu, O. R., and Salvador, K. A. (2014). Construction Delay in Nigeria: A Perception of Indigenous and Multinational Constructions Firms. Journal of Emerging Trends in Economics and Management Science (JETEMS), 5(3), 371-378.
- Adam, A., David, B., and Xavier, H. (2012). Project Execution Strategy Road Special Report for Global Carbon Capture and Storage Institute, Gurgaon, Haryana, India.
- Agbu, O. (2005). Oil and Environmental Conflicts, in A. Hassan Saliu (ed) Nigeria under Democratic Rule, 1999-2003, 2, Ibadan: University Press.
- Aibinu, A. A., and Jagboro, G. O. (2012). The Effect of Construction Delays on Project Delivery in the Nigerian Construction Industry. International Journal of Project and Management, 20(8), 593-599. https://doi.org/10.1016/S0263(02)00028-5.
- Al-Hazim, N., and Abusalem, Z. (2015). Delay and Cost Overrun in Road Construction Projects in Jordan. International Journal of Engineering and Technology 4(2), 288-293. https://doi.org/10.14419/ijet.V4124409.
- Ashwin, A. S., and Rahul, S. P. (2014). Identification of Critical Construction Delay Factors, International Journal of Latest Trends in Engineering and Technology (IJLTET), 3(4), 256-261.
- Asish, R., and Pratheeba, P. (2015). Study on Construction Sequence Delay for Road Infrastructure Projects, Journal of Mechanical and Civil Engineering 12(2), 15-21. https://doi.org/10.9790/1684.12261521.
- Aysha, S., Hussain, A., Naveed, A., Muhammed, N., and Nouman, A. (2015). Analysis of Key Performance Factors Affecting Residential Commercial Projects in Pakistan Arabian. Journal of Business and Management Review, 3(10), 9-14.
- Awodele, O. A., Ogunsemi, D. R., and Adeniyi, O. O. (2012). An Appraisal of Private Sector Participation in Infrastructure Development in the Nigeria Construction Industry: Lagos State as a case study. Journal of the Nigerian Institute of Quantity Surveyors, 1(1), 20-32.
- Aziz, R. F., and Abdel-Hakam, A. A. (2016). Exploring Delay Causes of Road Construction Projects in Egypt. Alexandria Engineering Journal, 55, 1515-1539. https://doi.org/10.1016/j.aej.2016.03.006.
- Benon, C. B., and Milton T. (2012). Measuring the Performance of Contractors in Government Construction Projects in Developing Countries: Uganda's Context, African Journal of Business Management 6(32), 9210-9217.
- Bromilow, F. J. (1974). Measurement and Scheduling of Construction Time and Cost Performance in the Building Industry, Chartered Builder, 10(9), 57.
- Choudhury, I., and Rajan, S. S. (2003). Time-Cost Relationship for Residential Construction in Texas. Amor R. (ed.) Proceeding of CIB W78's 20TH International Conference on Construction IT, Bridging the Distance, CIB Report 284. New Zealand, 23-25 April 2003, 73-80. Accessed 15/6/2019.
- Desai, M., and Desale, S. (2013). Study Factors Affecting Delay in Residential Construction Project for Nashik City in India. International Journal of Latest Trends in Engineering and Technology (IJLTET), 2(3), 115-124.
- Divya, R., and Ramya, S. (2015). Causes, Effects, and Minimization of Delays in Construction Projects. Proceedings of National Conference on Research Advance in Communication, Computation, Electrical Science, and Structures (NCRACCESS), 47-53.
- EnasFathi, T., and Pandey, R. (2013). Study of Delay in Project Planning and Design Stages of Civil Engineering Projects. International Journal of Engineering and Advanced Technology (IJEAT), 2(3), 456-461.
- Enshassi, A., Mohamed, S., and Madi, I. (2005). Factors Affecting Accuracy of Cost Estimation of Building Contracts in Gaza Strip. Journal of Financial Management of Property and Construction, 10(2), 115–125. https://doi.org/10.1108/1366438058000/069
- Ekanem, S. F. (2019). Impact of Delay on the Performance of Road Projects Procured by Niger Delta Development Commission, Nigeria. Unpublished PhD Thesis in the Department of Quantity Surveying, Faculty of Environmental Design and Management, Obafemi Awolowo University, Ile-Ife, Nigeria.
- Gebrehiwet, T., and Luo, H. (2017). Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study, Creative Construction Conference Premoisten, Croatia. Procedia Engineering 196, 366-374. https://doi.org/10.1016/j-preng.2017.07.212.
- Ghana Statistics Service (2019). http://www.Government Data/.erte.com.accessed; 3/7/2020.
- Harrell, F. E. (2011). Regression Modelling Strategies-with Application to Linear Models, Logistic Regression and Survival Analysis, New York: Springer-Verlag Inc, 215-221.
- Haseeb, M., Xinhai-Lu, A., Bibi, A., Maloof-ud, D., and Rabbani, W. (2011). Problems of Projects and Effects of Delays in the Construction Industry of Pakistan. Australian Journal of Business and Management Research, 1(5), 41-50.
- Hoffman, G. J. Jr. Thal, E. A., Webb, S. T., and Weir, D. J. (2007). Estimating Performance Time for Construction Projects. Journal of Management in Engineering 23(4),193-199. https://doi.org/10.1061/(ASCE)0742-597.
- Imonikebe, U. G. (2013). Constraints to Pig Farmers' Participation in Food Production as Occasioned by the Devastating Flood in Isoko North Local Government Area of Delta State, Nigeria. Scottish Journal of Arts, Social Sciences and Scientific Studies, 17(1), 13- 19.
- Isidiho, A. O., and Sabran, S. M. (2015). Socio-Economic Impact of Niger Delta Development Commission (NDDC) Infrastructure Projects in Selected Communities in Imo State, Nigeria. Asian Journal of Human and Social Science (AJHSS), 3(2), 109-113.
- Jhawar, A., and Bajpai, P (2014). Applying FMEA and ISM Technique to Identify Factors Causing Delay in Road Construction Projects. International Journal of Applied Engineering Research, 9(5), 517-524.
- Jike, V. (2005). The Political Sociology of Resource Control in the Niger Delta, A. Hassan Saliu (ed), Nigeria under Democratic Rule, 1999-2003, 2, Ibadan: University Press.
- Kaka, P. P., and Price, A. D. (1991). Relationship Between Value and Duration of Construction Projects. Construction Management and Economics, 9(4), 383-400. https://doi.org/10.1080/01446189100000030
- Khair, K., Farouk, H., Mohamed, Z., and Mohammad, R. (2016). Causes and Effects of Delay Factors in Road Construction Projects in Sudan. International Journal of Applied Engineering Research, 11(18), 9526-9533.
- Kulemeka, P. J., Kululanga, G., and Morton, D. (2015). Critical Factors Inhibiting Performance of Small- and Medium-Scale Contractors in Sub-Saharan Region: A Case for Malawi. Journal of Construction Engineering, (2015), 1-17. https://doi.org/10.1155/2015/927614
- Larsen, J., Shen, G., Lindhard, S., and Brunoe, T. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management and Engineering, 32(1), 04015032-1 – 04015032-10. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391
- Mahamid, I. (2011). Risk Matrix for Factors Affecting Cost Delay in Road Construction Projects Owners' Perspective. Engineering Construction and Architectural Management, 18(6), 609-619. https://doi.org/10.1108/09699981111180917
- Mahamid, I. Bruland, A., and Dmaidi, N. (2012). Causes of Delay in Road Construction Projects. Journal of Management in Engineering 28(3), 300-310. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096
- Mansfield, N., Ugwu, O., and Doran, T. (1994). Causes of Delay and Cost Overruns in Nigerian Construction Projects. International Journal of Project Management 12(4), 254-260. https://doi.org/10.1016/0263-7863(94)90050-7
- Mohammed, K. A., and Isah, A. D. (2012). Causes of Delay in Nigeria Construction Industry. Interdisciplinary Journal of Contemporary Research in Business, 4(2), 785-795.
- Mojekeh, M. O., and Eze, P. A. (2011). The Environmental Impact of Production and Sales of Sachet Water in Nigeria. African Research Review: An International Multidisciplinary Journal, Ethiopia, 5(4), 479-492. https://doi.org/10.4314/afrrev.v5i4.69298
- Mulla, S. S., and Waghmare, A. P. (2015). A Study of Factors Caused for Time and Cost Overruns in Construction Project and their Remedial Measures. Journal of Engineering Research and Applications, 5(1), 48-53.
- Ogunsemi, D. R., and Jagboro, G. O. (2006). Time-Cost Model for Building Projects in Nigeria. Construction Management and Economics, 24, 253-258. https://doi.org/10.1080/01446190500521041
- Olawale, Y., and Sun, M. (2010). Cost and Time Control of Construction Projects Inhibiting Factors and Mitigating Measures in Practice. Construction Management Economics 28(5), 509-526. https://doi.org/10.1080/01446190/003674519.
- Opawole, A. (2015). Assignments of Parties Obligation in Concession-Based Infrastructural Projects in South-Western, Nigeria. PhD Thesis in the Department of Quantity Surveying, Faculty of Environmental Design and Management, Obafemi Awolowo University, Ile-Ife, Nigeria.
- Otali, M., and Adewuyi, T. O. (2015). Project Duration Prediction Models Using Time - Cost Relationship in Public Building Projects in North Central, Nigeria. Nigerian Journal of Agriculture, Food and Environment, 11(1), 137-144.
- Pallant, J. (2007). SPSS Survival Manual - A Step by Step Guide to Data Analysis using SP55 for Windows, 3rd ed., England McGraw Hill, Open University Press, 1- 311.
- Ramabodu, M., and Verster, J. (2010). Factors Contributing to Cost Overrun of Construction Projects. Proceeding of ASOCSA, 5th Built Environment Conference Durban South Africa.
- Patil, K. S., Gupta, A., Desai, D., and Sajane, A. (2013). Causes of Delay in Indian Transportation Infrastructure Projects. International Journal of Research in Engineering and Technology (IJRET), 2(11), 71-80. https://doi.org/10.15623/ijret.2013021/013
- Rawat, D. S., and Sharmai, S. (2016). The Development of a Road Network and Its Impact on the Growth of Infrastructure: A Study of Almora District in the Central Himalaya. Journal of Mountain Research and Development, 17(2), 117-126. https://doi.org/10.2307/3673826.
- Shahid, A., Ahmad, H., Ahmad, N., Shafique, M. N., and Amjad, N. (2015). Analysis of Key Performance Factors Affecting Residential Construction Projects in Pakistan. Arabian Journal of Business and Management Review 3(10), 9-14.
- Shahsavand, P., Marefat, A., and Parchamijalal, M. (2018), "Causes of Delays in Construction Industry and Comparative Delay Analysis Techniques with SCL Protocol", Engineering, Construction and Architectural Management, 25(4), 497-533. https://doi.org/10.1108/ECAM-10-2016-0220.
- Tabachnick, B. G., and Fidell, L. S. (2007). Using Multivariate Statistics. Third Edition., Harper Collins, New York.
- Towhid, P., and Amiruddin, I. (2012). Causes and Effects of Delay in Iranian Construction Projects. International Journal of Engineering and Technology, 4(5), 598-601. https://doi.org/10.7763/ijet2012V4.441.
- Ujene, A. O. (2014). Integrating Environmental Priority Concerns in Building Planning and Production in Niger Delta, Nigeria. Journal of Architecture, Planning, and Construction Management, 4(2), 37-56.
- Umoren, O. (2014). Site Analysis and Report, A Basic Requirement in Planning for Construction. A Paper Delivered on October 9 – 11. The Nigerian Institute Quantity Surveyors National Training Workshop, Uyo, Akwa Ibom State, Nigeria.
How to Cite
Ekanem, S. F., Opawole, A., & Adewuyi, T. O. (2020). EFFECTS OF DELAY ON COST PERFORMANCE OF ROAD CONSTRUCTION PROJECT: CASE OF NIGER DELTA DEVELOPMENT COMMISSION PROJECTS IN NIGERIA. Journal of Contemporary Research in the Built Environment, 4(1), 1-16. https://doi.org/10.68128/jocrebe.2020.odhjnjwy
S. F. Ekanem, A. Opawole, and T. O. Adewuyi, "EFFECTS OF DELAY ON COST PERFORMANCE OF ROAD CONSTRUCTION PROJECT: CASE OF NIGER DELTA DEVELOPMENT COMMISSION PROJECTS IN NIGERIA," Journal of Contemporary Research in the Built Environment, vol. 4, no. 1, pp. 1-16, March 2020. doi: 10.68128/jocrebe.2020.odhjnjwy