Research Article

EFFECTS OF OVERHEAD COST OF CIVIL ENGINEERING PROJECTS IN NIGERIA

1 Department of Quantity Surveying, University of Benin, Benin-City, Edo State
* Corresponding author: chukwuemeka.ogbu@uniben.edu
Published: Mar, 2019
Pages: 1-14
Views: 22
Downloads: 8

Abstract

Purpose: “General items” is an important cost center in civil engineering projects given the complexities of facilitative works and support services that are normally required in such projects. However, extant literature makes little or no difference between preliminaries in building projects and general items in civil engineering projects. This study, which focuses on overhead costs in civil engineering projects, was carried out to: (1) assess the factors affecting overhead cost of civil engineering projects, (2) determine the relationship between the factors and the overhead costs of civil engineering projects and; (3) determine the frequency of use of overhead cost items in civil engineering projects. Design/methodology/approach: Respondents were conveniently selected from civil/structural engineers and quantity surveyors who have participated in civil engineering projects (n=73) in Nigeria. The data were analyzed using percentages, relative importance index, multiple regression and factor analysis. Findings: It was found that the most important factor affecting the overhead cost of civil engineering projects is delayed payment. Based on factor analysis, it was concluded that the factors affecting overhead costs of civil engineering projects are either project or contractor related. These two groups of factors were found to have significant effects on the overhead cost of civil engineering projects. Provisions for water supply, setting out and handover were found to be the predominant general items allowed in civil engineering projects. The possibility of payment delays should be assessed while estimating the cost of general items, and only applicable general items should be priced. Research limitations/implications: Many types of civil engineering projects were considered in this study. Future studies may look at how overhead costs differ for different types of civil engineering projects. Social implication: Delayed payment avoidance by the government will have a positive effect on the overhead and, ultimately, the overall costs of civil engineering projects. Originality/value: This study ascertained the frequency of use of general items in civil engineering projects. It also determined the domains of the variables that affect the overhead cost of civil engineering projects. Most previous studies on construction project overhead costs were based on building projects

References

  1. Assaf, S. A., Bubshait, A. A., Atiyah, S., & Al-Shahri, S. (2001). The Management of Construction Company Overhead Costs, International Journal of Project Management, 19(5), pp. 295-303.
  2. Chan, C. T.W. (2012). The principal factors affecting construction project overhead expenses: An exploratory factor analysis approach, Construction Management and Economics, 30:10, 903-914, DOI: 10.1080/01446193.2012.717706.
  3. Chan, C. T., & Pasquire, C. (2004). An analysis for the degree of accuracy in construction project indirect costs. The Journal of Cost Analysis & Management, 6(1), 46-66.
  4. Chao, L. C. (2008). Estimation of contractor's project overhead rate as research on building cost. In: R.D.G Amaratunga, and R.P Haigh. Proceeding of Building Resilience, (pp.74-82). Salford: School of the Built Environment, University of Salford http://eprints.hud.ac.uk/id/eprint/30829/1/No.18%20Performance%20measurement%20in%20con.pdf#page=99.
  5. Cilensek, R. (1991). Understanding constructor overhead, Cost Engineering AACE 33(12): 21–30.
  6. Dagostino, F. R. (2002). Estimating in building construction 6th edition. New Jesey: Prentice-Hall
  7. Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International journal of project management, 30(4), 479-489.
  8. ElSawy, I., Hosny, H., & Razek, M. A. (2011). A neural network model for construction projects site overhead cost estimating in Egypt. arXiv preprint arXiv:1106.1570.
  9. Eksteen, B. & Rosenberg, D. (2002), "The management of overhead costs in construction companies" in Greenwood, D. (Ed.), 18th Annual ARCOM Conference, 2-4 September 2002, and University of Nothumbria, Vol. 1 Association of Researchers in Construction Management, pp. 13-22.
  10. Enshassi, A., Rashid Abdul Aziz, A., & El Karriri, A. A. (2008). Investigating the overhead costs in construction projects in Palestine. Journal of Financial Management of Property and Construction, 13(1), 35-47.
  11. Fellows R. L. A. (1997). Research methods for construction. Oxford: Blackwell Science.
  12. Field A. (2005). Discovering statistics using SPSS. 2nd ed. Thousand Oaks (CA): Sage.
  13. Hesami, S. & Lavasani, A. (2014). Identifying and Classifying Effective Factors Affecting Overhead Costs in Constructing Projects in Iran. International Journal of Construction Engineering and Management 2014, 3(1): pp 24-41
  14. Jimoh, R. A., & Adama, S. M. (2011). Assessment of preliminaries in relation to the total cost of renovation work in public schools in Abuja, Nigeria. In ICEC IX World Congress Assessment (pp. 1-9).
  15. Juszczyk, M., Leśniak, A. (2019). Modelling construction site cost index based on neural network ensembles. Symmetry, 11(3), 411.
  16. Kaiser, H.F. (1974). An index of factorial simplicity. Psychometrika 39, 31–36.
  17. Kumaraswamy, M. M., & Chan, D. W. (1998). Contributors to construction delays. Construction Management & Economics, 16(1), 17-29.
  18. Leśniak, A., & Juszczyk, M. (2018). Prediction of site overhead costs with the use of artificial neural network based model. Archives of Civil and Mechanical Engineering, 18(3), 973-982.
  19. Lo, T. Y., Fung, I. W., & Tung, K. C. (2006). Construction delays in Hong Kong civil engineering projects. Journal of construction engineering and management, 132(6), 636-649.
  20. Nabil, I., & El-Riyati, A. (2015). An overhead costs assessment for construction projects at Gaza Strip. American Journal of Civil Engineering, 3(4), 95-101. doi: 10.11648/j.ajce.20150304.11.
  21. Nigerian Institute of Quantity Surveyors (2015). Building and Engineering Standard Method of Measurement Fourth Edition. Abuja: Nigerian Institute of Quantity Surveyors.
  22. Patil, S. & Bhangale, P. (2014). Overhead cost in construction industry. International Journal of Industrial Engineering & Technology (IJIET) vol. 4(2). ISSN(P): 2277-4769;
  23. Peurifoy, R. L., & Oberlender, G. D. (2002). Estimating construction costs 5th edition. New York: McGraw-Hill.
  24. Plebankiewicz, E., & Leśniak, A. (2013). Overhead costs and profit calculation by Polish contractors. Technological and Economic Development of Economy, 19(1), 141-161.
  25. Ronald, A. M., & Lumbantoruan, H. (2019, April). Analysis of Project Cost Management Indicators at Residential Buildings (Case Study: Building Construction Project in Rusun Penggilingan Jakarta). In IOP Conference Series: Materials Science and Engineering (Vol. 508, No. 1, p. 012044). IOP Publishing.
  26. Siskina, A., Joudis, A., & Viciene R. A (2009). Evaluation of the competitiveness of construction company overhead costs. Journal of civil engineering and management. 15(2): 215–224.
  27. Ujene, A.O., Idoro, G.I, & Odesola, I.A. (2013). Contractors Perceptions of Effects of Project Overhead Costs on Building Project Performance in South-South of Nigeria. Civil Engineering Dimension, 15(2), 102-113.
How to Cite

Ogbu, C. P., & Imafidon, M. O. (2019). EFFECTS OF OVERHEAD COST OF CIVIL ENGINEERING PROJECTS IN NIGERIA. Journal of Contemporary Research in the Built Environment, 3(1), 1-14. https://doi.org/10.68128/jocrebe.2019.1v4qbrir

C. P. Ogbu, and M. O. Imafidon, "EFFECTS OF OVERHEAD COST OF CIVIL ENGINEERING PROJECTS IN NIGERIA," Journal of Contemporary Research in the Built Environment, vol. 3, no. 1, pp. 1-14, March 2019. doi: 10.68128/jocrebe.2019.1v4qbrir

Share this article:
Facebook X / Twitter LinkedIn