EVALUATING CAUSES OF CHANGE IN BUILDING CONSTRUCTION PROJECTS
1 Department of Building, University of Uyo, Uyo, Nigeria
* Corresponding author: femifavour.ff@gmail.com
* Corresponding author: femifavour.ff@gmail.com
Abstract
Purpose: Change in building construction project is inevitable and can occur at any stage, it has
different source and reason due to involvement of many participants. Therefore, the study gives
insight into causes of these changes and its consequences on building project performance.
Design/methodology/approach: Descriptive and survey research method was used to evaluate
the perception of construction participants and stakeholders to evaluate significant causes of
change and effects of change order on performance of building construction projects. 125 well
structured, cross-sectional questionnaires were distributed and data obtained were analysed
using descriptive, relative importance index and Kruskal-Walis tests.
Findings: Feedback from the respondents revealed the most significant causes of change in
building construction projects to include change of plans by owners followed by change in
design, poor communication among the construction participants, owners’ financial difficulties
and owners’ change of schedule. Further findings on the effect of change order on the
performance of building construction projects shows that on the general notes, cost overrun is
the most prevalent effect followed by quality standard enhanced, time overrun, additional
money for contractor overhead and work-on-hold (in descending order).
Research limitation/implications: This study is limited in scope to all such building
construction projects in the study area (public buildings, commercial, hospital and others), also
restricted to the opinion of 104 participants who duly completed and return their questionnaire.
It has found that managing changes at project level is a critical problem faced by the construction
industry. An understanding of the causes of change (that leads to change order) would be helpful
for building construction professional and participants in managing change/variation orders.
Practical implications: Introduction of change management procedure in the contract
document will enhance smooth delivery of building projects with less disputes. The change will
be managed to maximise the benefit and minimise penalties. It is also recommended that the
Ministries (federal and state) in charge of housing should establish or have a well-defined
system of managing changes in Government building construction projects rather than abrupt
calling for unjustified variation by their contractors or suppliers.
Originality/value: The study highlighted and established changes in building construction
projects and the effects of change order on performance only in Akwa Ibom state.
Keywords
Change; change order; variation; management; construction projects.
How to Cite
Olasunkanmi, F. O., & Oladokun, M. G. (2019). EVALUATING CAUSES OF CHANGE IN BUILDING CONSTRUCTION PROJECTS. Journal of Contemporary Research in the Built Environment, 3(2), 101-120. https://doi.org/10.68128/jocrebe.2019.roqb6wo1
F. O. Olasunkanmi, and M. G. Oladokun, "EVALUATING CAUSES OF CHANGE IN BUILDING CONSTRUCTION PROJECTS," Journal of Contemporary Research in the Built Environment, vol. 3, no. 2, pp. 101-120, September 2019. doi: 10.68128/jocrebe.2019.roqb6wo1