Research Article

EVALUATION OF FACTORS INFLUENCING PLANNING EFFORTS IN BUILDING PROJECTS IN UYO, NIGERIA

1 Department of Building, Federal University of Technology, Minna, Nigeria
2 Department of Estate Management and Valuation, Federal University of Technology, Minna, Nigeria
* Corresponding author: builderolubajo@gmail.com
Published: Sep, 2017
Pages: 95-105
Views: 17
Downloads: 7

Abstract

Purpose: This study investigates the factors influencing planning efforts in building projects in Uyo, Nigeria. The focus is specific on those factors that significantly affect the pre-contract planning stages of building projects.

 

Design/methodology/approach: A survey approach was adopted in the collection of data among key professional consultants involved in building project planning and execution. A sample selection of Architects (32), engineers (43) and Quantity Surveyors (38) was drawn from 56 project sites and 9 consulting firms in the study area adding up to a sample size of 113 professional consultants. Structured questionnaire were administered with 81.4% response rate.

 

Finding: The outcome from analysis of the square sum of ranks indicates factors such as client's demand, client's policy and planning procedures as the most significant factors influencing pre-contract building project planning efforts.

 

Research limitations/implications: The investigation of the factors was limited to those most applicable to the pre-contract planning stage of building projects.

 

Originality/value: The conclusion is that clients have significant influence on the amount of efforts invested in planning and performance of building construction projects.

References

  1. Chitkara, K. K. (2011). Construction Project Management-Planning, Scheduling and Controlling. 2nd Ed. New Delhi: Tata McGraw-Hill Publishing Company Ltd.
  2. Cooke, B. & Williams, P. (2009) Construction planning, programming and control (3rd Ed). United Kingdom: Blackwell.
  3. Dvir, D. Raz, T. & Shenhar, J. (2003). An Empirical Analysis of the Relationship between Project Planning & Project Success. International Journal of Project Management, 21(2), 1-7.
  4. Frank, H. & McCaffer, R. (2001). Modern Construction Management.5th Ed. London: Blackwell Science.
  5. Frederick, S. M. & Ricketts, J.T. (2001), Building design and construction Handbook (6th Ed). London: McGraw Hill Publishing Company Ltd.
  6. Idoro, G. (2011). The influence of project documents on the outcome of construction projects procured by traditional contracts in Nigeria, Journal of Construction in Developing Countries. 17(1), 1-19.
  7. Idoro, G. (2010) Project Planning as a Correlate of Project Outcome in the Nigerian Construction Industry. International Journal of Project Planning and Finance. 1(1), 39-59.
  8. International Federation of Red Cross & Red Crescent Societies, (2000). Disaster Preparedness Training Programme, Resource module. Retrieved from http://www.ifrc.org/Global/Disproin.pdf . On 25th May 2011.
  9. Kerzner, H. (2006). Project Management: A Systems Approach to Planning, Scheduling and Controlling. 9th edition, John Wiley and Sons.
  10. Mohamed, A., (2010) Project planning manager's contribution. Journal of Project Management World Today, 12(4), 1-7.
  11. Meredith J. R. & Mantel S. J. (2006). Project Management - A Managerial Approach. (6th Ed.) John Wiley and Sons.
  12. National Population Commission (2006), National Census results.
  13. Patrick, H. & Geffner, H. (2001), Heuristic planning with Time and resources. Proceedings of the International Conference on Artificial Intelligence Workshop on planning Resources. Retrieved from http://www.rakaposhi.eas.asu.edu/ese574/tp4.pdf on 25th May 2011.
  14. Puthamont, S. & Charoenngam, C. (2004) Strategies Project selection in Government Organisations. Proceedings of International Symposium on Globalization and Construction. CIB 2004, W107, TG23 School of Civil Engineering, Asian Institute of Technology, Thailand. Retrieved from http://www.irbnet.de/daten/iconda/CIB6067.pdf. On 25th May 2011.
  15. Zwikael, O. & Sadeh, A. (2007). Planning effort as an effective risk management tool. Journal of Operations Management, 25(4), 755-76.
  16. Zwikael, O. (2009). Critical planning process in construction projects. Construction Innovation, 9 (4), 372-387.
How to Cite

Olubajo, O. O., & Kuma, S. . S. (2017). EVALUATION OF FACTORS INFLUENCING PLANNING EFFORTS IN BUILDING PROJECTS IN UYO, NIGERIA. Journal of Contemporary Research in the Built Environment, 1(2), 95-105. https://doi.org/10.68128/jocrebe.2017.2t5zk3dr

O. O. Olubajo, and S. . S. Kuma, "EVALUATION OF FACTORS INFLUENCING PLANNING EFFORTS IN BUILDING PROJECTS IN UYO, NIGERIA," Journal of Contemporary Research in the Built Environment, vol. 1, no. 2, pp. 95-105, September 2017. doi: 10.68128/jocrebe.2017.2t5zk3dr