FACTORS INFLUENCING THE EFFECTIVENESS OF RISK MANAGEMENT IN HOUSING PROJECTS PROCURED WITH SELECTED METHODS IN AKWA IBOM STATE
1 Works Department, Ikot Ekpene L.G.C. Akwa Ibom State. Nigeria
2 Department of Building, University of Uyo, Akwa Ibom State, Nigeria
* Corresponding author: ujenetony@yahoo.com
2 Department of Building, University of Uyo, Akwa Ibom State, Nigeria
* Corresponding author: ujenetony@yahoo.com
Abstract
Purpose: The awareness and insight of the factors influencing risk management is essential in
the effective management of projects delivered with any procurement method. The study aimed
at providing insight into how several factors influence the effectiveness of risk management
practices of housing projects procured by traditional, direct labour and, labour only methods
with a view to enhancing construction projects delivery in Akwa Ibom State.Design/methodology/approach: A cross-sectional survey approach was used for the study.
Ninety-nine (99) copies of questionnaire were retrieved from purposively selected
representatives of construction firms operating in the study area. Twenty-five factors were
identified from literature and presented for respondents’ assessment. Data collected were
analysed using relative influence index, while Kruskal Wallis was used to test the hypothesis.Findings: It has been established that the five most important factors influencing the
effectiveness of risks management in traditional, direct labour and labour-only procurement
methods are; timing, environmental factors, funds allocation for risk exercise, complexity and
top management support. The result also shows that 4.0% of the whole factors has very high
influence, 60% have high influence, while 36% of the evaluated factors have moderate influence
on the effectiveness of the procurement methods, with all the methods exhibiting similar
influence.Research limitations/implications: The limitations include the use of only the perception of
purposively selected representatives of construction firm in Akwa Ibom state and only selected
procurement methods. The contribution to knowledge is that this study has established the
current level of effectiveness of risk management in some procurement methods in the study
area.Practical implications: It is recommended that that advanced formal and informal training in
risk management and prioritization of the control of the factors influencing their effectiveness
should be regularly conducted among the stakeholders involved in the delivery of housing
projects in the study area. Originality/value: The study revealed the level of influence which the identified risk factors
have on the management of risks in of housing projects procured with different methods, as well
as the variations among the factors in the procurement methods.
Keywords
Originality/value: The study revealed the level of influence which the identified risk factors have on the management of risks in of housing projects procured with different methods
as well as the variations among the factors in the procurement methods.
References
- Alashwal, A. M and Al-Sabahi, M. H. (2018). Risk Factors in Construction Projects during Unrest Period in Yemen. Journal of Construction in Developing Countries, 23(2), 43–62.
- Akpan, G. A. and Usoro, E. B. (2011). Problems and strategies for private sector development in Akwa Ibom state, Nigeria. Journal of Sustainable Development in Africa, 13 (8), 129-141.
- Akpan, P. U. (2014). Oil exploration and security challenges in the Niger -delta region: A case of Akwa Ibom state, Nigeria. IOSR Journal of Research & Method in Education, 4(2), 41-48.
- Akinkumi, O. G., Aghimien, D. O. and Awodele, O.A. (2018). Appraising the use of Labour-Only Procurement System for Building Construction in Nigeria. Organization, Technology and Management in Construction. 10, 1719-1726.
- Akobi, G., (2012). The Comparison of Traditional and Direct Labour Procurement Methods Adopted by the Nigerian army. A M.Sc thesis in the Department of Building, Faculty of Environmental Design, A. B. U. Zaria.
- Alabi, A.O. (2018). Assessment of Risk involved in Housing Projects Procured Using Public Private Partnership System in Nigeria, International Journal of Economic, Commerce and Management, 6(12), 443-455.
- Aminu, A. B. (2013). Risk Management in Nigerian Construction Industry. An M.Sc Thesis, Institute of Graduate Studies and Research, Eastern Mediterranean University, Gazimagusa, North Cyprus.
- Babatunde, S. O., Opawole, A. and Ujaddughe, I. C. (2010). An Appraisal of Project Procurement Methods in the Nigerian Construction Industry. Civil Engineering Dimension. 12(1), 1-7.
- Banaitiene, N. and Banaitis, A. (2012). Risk Management in Construction projects (http://creativecommons.org/licenses/by3.0) http://dx.doi.org/10.5772/51460, accessed 23rd September, 2015.
- Chartered Institute of Building (2010), A Report on Exploring Procurement in the Construction Industry. Englemere, Kings Ride, Ascot Berkshire SL5 7TB, United Kingdom.
- Cleland, D. I. and Ireland, R. L. (2002). Project Management: Strategic Design and Implementation (Forth Edition). New York: McGraw-Hill.
- Cox, I. D., Morris, J. P., Rogerson, J. H. and Jared, G. E. (1999). A quantitative study of post contract award design changes in construction, Construction Management and Economics, 17(4), 427-39.
- Davis, P. Love, P. Barccarini, D. (2008), Construction Innovation Report on Building Procurement Methods. Curtin university of Technology.
- El-Agha, O.I. (2013). Factors Affecting the Selection of Procurement Methods in the Construction Projects in Gaza Strip, An M.Sc. Thesis in Civil Engineering - Construction Management, The Islamic University of Gaza.
- Enshassi, A., Mohamed, S. and Abushaban, S. (2009). Factors affecting the performance of construction projects in the Gaza Strip, Journal of Civil Engineering and Management, 15(3), 269–280.
- Ghahramanzadeh, M. (2013). Managing risk of construction projects: A case study of Iran. PhD Thesis, University of East London, UK. Retrieved December 20th, 2019 from: http://hdl.handle.net/10552/3502.
- Gyamfi, T. A., Boadaa, R. and Adu-Fosu, B. (2016). Risk Analysis of Procurement Options: Implications for Construction Firms in Ghana. International Journal of Sciences: Basic and Applied Research (IJSBAR), 28(1), 90-102.
- Iboh, A. A., Adindu, C. C. and Oyoh, A. J. (2013). Public Private Partnership Construction Project Disputes in Nigeria. Journal of Research in National Development, 11(1), 6-11.
- James, E. E., Akpan, P. A., Essien, A. U. and Ekpo, K. J. (2012). The Pattern of Housing-Health Status among Residential Zones in Uyo Metropolis, Akwalbom State, Nigeria, Journal of Environmental Issues and Agriculture in Developing Countries, 4(3), 29-35.
- Kerzner, H. (2003). Project Management: A System Approach to Planning, Scheduling and Controlling. 8th Ed. New Jersey: John Wiley & Sons.
- Kadiri, D. S. Ogunkola, O. M. (2014), Assessment of Procurement Methods Based on Clients Selection Criteria in Ogun State, Nigeria, Covenant Journal of Research in the Built Environment. 2(1), 31-41.
- National Bureau of Statistics (2015). Nigerian Construction Sector: Summary of Report 2010-2012.
- Ngundo, J. M. (2014). Factors Affecting Effectiveness of Risk Management in Public Housing Construction Projects In Kenya: A Case of Kibera Slum Upgrading Housing Scheme in Nairobi, A Master of Arts in Project Planning and Management of The University of Nairobi.
- Ogunsanmi, O. (2012), Comparison of Procurement Characteristics of Traditional and Labour-Only Procurement in Housing Projects in Nigeria, Civil and Environmental Research, 2(8), 1-10.
- Ogunsanmi, O. E., Salako, O. A. and Ajayi, O. M. (2011). Risk Classification Model for Design and Build Projects, Journal of Engineering, Project, and Production Management, 1(1), 46-60.
- Osipova, E. (2008). Risk management in construction projects: a comparative study of the different procurement options in Sweden, Unpublished Licentiate Thesis, Department of Civil, Mining and Environmental Engineering, Luleå University of Technology.
- Ozcan, G. (2008). A Generic Risk and Vulnerability Assessment Framework for International Construction Projects. An Unpublished M. Sc. Thesis in the Department of Civil Engineering Middle East Technical University.
- Perera, B. A. K. S., Rameeddeen, R. Chileshe, N. and Hosseinin, M. R. (2014).Enhancing the Effectiveness of Risk Management Practices in Sri Lankan Construction Projects: A Delphi Approach. International Journal of Construction Management, 14(1), 1-19.
- PMI Project Management Institute, (2004), a Guide to the Project Management Body of Knowledge: PMBOK 3rd Edition, Pennsylvania: Project Management Institute.
- Rao, T.V.M. and Mak, C.L. (2001). A risk management model for improving operation and maintenance activities in electricity transmission networks. The Journal of the Operational Research Society, 52(2), 125–134.
- Rashid, A., Taib, M., Ahmad, W., Basiron, W., Nasid, M., Ali, W., and Zainordin, Z. (2006). Effect of procurement systems on the performance of construction projects. Symposium conducted at the meeting of the International Conference on Construction Industry 2006 (ICCI 2006), Padang, Indonesia.
- Ropel, M. and Gajewska, E. (2011). Risk Management Practices in a Construction Project –A Case Study, An M,Sc Thesis in the Department of Civil and Environmental Engineering, Division of Construction Management. Chalmers University of Technology, Sweden.
- Sanda, Y. N., Anigbogu, N. A., Nuhu, Z. Y. and Olumide, O. S. (2020). A Life-Cycle Framework for Managing Risk in Public Private Partnership in Housing Project; Journal of Engineering, Project and Production Management. 10(1), 27-34.
- Serpella, A. F., Ferrada, X. Howard, R., Rubio, L. (2014). Risk Management in Construction Projects: A Knowledge– Based Approach. Journal of Social and Behavioural Sciences (119), 653-663.
- Udoh, N. (2014). The Determinants and Implications of Rural-Urban Migration in Nigeria. African Journal of Social Sciences, 4 (3), 133-143.
- Ugwu, O. O. and Haupt, T. C. (2007). Key performance indicators and assessment methods for infrastructure sustainability – a South African construction industry perspective, Building and Environment, 42, 665–680.
- Ujene, A. O. and Adewuyi, T. O. (2016). Residential buildings procurement with labour only method: performance evaluation among federal income earners in Akwa Ibom State. Journal of Environmental Sciences, 17(1&2), 39-53.
- Waziri, B. S. and Bala, K. (2014). Actualizing Nigeria's vision 20:2020 Imperatives of the Construction sector, Civil and Environmental research, 6 (6), 69-75.