IMPACT OF PAYMENT PROBLEMS ON THE PERFORMANCE OF MICRO, SMALL AND MEDIUM SIZE CONSTRUCTION CONTRACTORS
1 Department of Quantity Surveying, University of Uyo, Uyo, Akwa Ibom State, Nigeria
2 Department of Building, Akwa Ibom State Polytechnic, Ikot Ekpene, Nigeria
* Corresponding author: fidelischristian@uniuyo.edu.ng
2 Department of Building, Akwa Ibom State Polytechnic, Ikot Ekpene, Nigeria
* Corresponding author: fidelischristian@uniuyo.edu.ng
Abstract
Purpose: Prompt payment has serious implication for the success of construction contracts, and
this is particularly so where smaller construction contractors are involved since they rely heavily
on cash flow to sustain their business operations. Despite the existence of contractual provisions
and legislations, payment problems are still endemic in the construction industry. The study was
therefore undertaken to investigate the causes of payment problems, and their impact on the
contractual and business performance of micro, small and medium size construction contractors.
Design/methodology/approach: Sixty-two (62) construction contractors in Akwa Ibom State
in the micro, small and medium size category were surveyed using a well-structured
questionnaire.
Findings: The result reveals that the practice of pay-when-paid, delay in certification of interim
payment, involvement of too many parties in the process of honouring certificate and failure to
agree on valuation of work done rank as important factors responsible for payment problems.
In addition, increase in the construction costs, decrease in contractors’ profitability and delay in
project completion time rank as the major effect of payment problems. The study also concludes
that there is no difference in the perception of micro, small and medium-sized firms on the
impact of payment problems.
Originality/value: In spite of the importance of smaller contractors in the construction
economy of Nigeria, studies on payment problems affecting this financially weak and
vulnerable segment of the construction sector are scarce. Investigation of the important factors
responsible for payment problems would provide insight to construction industry stakeholders
in devising mitigating measures. Overall, this will improve the efficiency, sustainability and
viability of the construction sector.
Keywords
Construction contractors; contingent payment; payment problems; performance; profitability
References
- Read a file, ran a command
- Abdul-Rahman, H., Wang, C., Takim, R. & Wong, S. (2011). Project schedule influenced by financial issues: evidence in construction industry, Scientific Research and Essays, 6(1), 205-212.
- Agumba, J. N. & Fester, F. C. (2011). Identifying tools and techniques for managing construction project delivery in small and medium enterprises in South African construction industry, Journal of Social and Development Sciences, 2 (4), 204-213.
- Amoako, A. B. (2011). The effect of delayed payment on cash flow forecasting of Ghanaian road contractors. Unpublished Master’s Thesis submitted to the Institute of Distance Learning, Kwame Nkrumah University of Science and Technology.
- Asuquo, C. F., Ogbu, C. P. & Akinsiku, O. E. (2014). Factors influencing development of small construction companies in Abia and Akwa Ibom States, Nigeria. Proceedings of the CIB W107 2014 International Conference, Lagos, Nigeria, 28th-30th January, 2014.
- Australian Procurement and Construction Council [APCC] (1996). National action on security of payment in the construction industry. Deakin West Australia Capital City: Australian Procurement & Construction Council Inc.
- Cheng, T., Soo, G., Kumaraswamy & Jin, W. (2009). Security of payment for Hong Kong construction industry – workable alternatives and suggestions, Building Journal, 60-77.
- Federal Government of Nigeria [FGN] (2007). Public Procurement Act 2007. Lagos; Federal Government Printer.
- Federal Government of Nigeria [FGN] (2010). Draft National Policy on Micro, Small and Medium Enterprises. Abuja; Small and Medium Enterprise Development Agency of Nigeria (SMEDAN).
- Harris, F. & McCaffer, R. (2001). Modern construction management (5th Ed.). Oxford: Blackwell Science Ltd.
- Hasmori, M.F., Ismail, I. & Said, I. (2012). Issues of late and non-payment among contractors in Malaysia. Proceedings of International Conference on Business and Economic Research, Bandung, Indonesia, 12-13 March, 2012.
- Hou, W., Liu, Z. & Chen, D. (2011). Payment problems, cash flow and profitability of construction project: A system dynamics model, World Academy of Science, Engineering and Technology, 58, 693-699.
- Judi, S. S. & Rashid, R. A. (2010). Contractor’s right of action for late on non-payment by the employer, Journal of Surveying, Construction and Property, 1(1), 65-95.
- Kaka, A. P. (2001). The case for re-engineering contract payment mechanisms. In: Akintoye, A (Ed.), 17th Annual ARCOM Conference, 5-7 September 2001, University of Salford. Association of Researchers in Construction Management, Vol. 1, 371-9.
- Munaaim, M. E. C., Danuri, M. S. M. & Abdul-Rahman, H. (2007). Is late or non-payment a significant problem to Malaysian contractors? Journal of Design and the Built Environment, 3 (1), 35-50.
- Nasser, A. H. (2013). The effect of payment delay on construction projects in Gaza Strip. Unpublished M.Sc. Thesis, The Islamic University of Gaza – Palestine.
- New Zealand Law Commission (1999). Protecting construction contractors. Study Paper 3. Wellington, New Zealand.
- Oladimeji, O. & Ojo, G. K. (2012). An appraisal of indigenous limited liability Construction Company in South-West Nigeria. In Laryea, S., Agyepong, S.A., Leiringer, R. and Hughes, W. (eds.). Proceedings of 4th West African Built Environment Research (WABER) Conference, July 24-26, 2012; Abuja, Nigeria, pp 1095-1109.
- Olusegun, A. E. & Michael, A. O. (2011). Abandonment of construction projects in Nigeria: causes and effect, Journal of Emerging Trends in Economics and Management Sciences, 2(2), 142-145
- Prisms Economics and Analysis (2013). The need for prompt payment legislation in the construction industry. Ontario: Prisms Economics and Analysis.
- Ramachandra, T. & Rotimi, J. O. (2011). The nature of payment problems in the New Zealand construction industry, Australasian Journal of Construction Economics and Building, 11 (2) 22-33
- Ramachandra, T. & Rotimi, J.O.B. (2012a). Liquidation and its effect on construction trade creditors in New Zealand, Journal of Financial Management of Property and Construction, 17(2), 166-175.
- Ramachandra, T. & Rotimi, J.O.B. (2012b). Construction payment delays and losses: perceptions of New Zealand. Proceeding of PMI New Zealand Chapter Annual Conference, Wellington, 24-26 September, 2012.
- Ramachandra, T. & Rotimi, J.O.B. (2015). Causes of payment problems in the New Zealand construction industry, Construction Economics and Building, 15(1), 43-55.
- Supardi, A. Adnan, H. & Mohammed, M. F. (2011). Security of payment regime in construction industry: Are Malaysian sub-contractors ready? The Built and Human Environment Review, 4 (1), 122-137.
- The Law Reform Commission of Western Australia (1999). Financial protection in the building and construction industry. Project Report No. 82. Perth, Western Australia: Law Reform Commission of Western Australia.
- Thwala, W. D. & Mvubu, M. (2009). Problems facing small and medium size contractors in Swaziland, Journal of Service Science & Management, 2, 353-361.
- Ugochukwu, S. C. & Onyekwena, T. (2014). Participation of indigenous contractors in Nigerian public sector construction projects and their challenges in managing working capital, International Journal of Civil Engineering, Construction and Estate Management, 1(1), 1-21.
- Uroko, C. (2012). Growth prospect seen as investors focus on construction industry. Businessday Newspaper, Thursday, May 24, 2012.
- Ye, K. M. & Rahman, H. A. (2010). Risk of late payment in the Malaysian construction industry, World Academy of Science, Engineering and Technology, 41, 538-546.
Cited By (1)
Works that cite this article, via Crossref Cited-by.
- A Markov Chain Framework for Assessing Owner Payment Reliability across Multiple Construction Projects . Journal of Construction Engineering and Management (2026) . https://doi.org/10.1061/JCEMD4.COENG-18847
How to Cite
Asuquo, C. F., & Effiong, E. F. (2017). IMPACT OF PAYMENT PROBLEMS ON THE PERFORMANCE OF MICRO, SMALL AND MEDIUM SIZE CONSTRUCTION CONTRACTORS. Journal of Contemporary Research in the Built Environment, 1(1), 35-46. https://doi.org/10.68128/jocrebe.2017.puffjmsi
C. F. Asuquo, and E. F. Effiong, "IMPACT OF PAYMENT PROBLEMS ON THE PERFORMANCE OF MICRO, SMALL AND MEDIUM SIZE CONSTRUCTION CONTRACTORS," Journal of Contemporary Research in the Built Environment, vol. 1, no. 1, pp. 35-46, March 2017. doi: 10.68128/jocrebe.2017.puffjmsi