Research Article

RISK MANAGEMENT EFFECTIVENESS IN HOUSING PROJECTS: A COMPARATIVE EVALUATION IN SELECTED PROCUREMENT METHODS IN AKWA IBOM STATE

1 Department of Building, University of Uyo, Akwa Ibom State, Nigeria
2 Works Department, Ikot Ekpene L.G.C. Akwa Ibom State. Nigeria
* Corresponding author: ujenetony@yahoo.com
Published: Mar, 2020
Pages: 36-54
Views: 30
Downloads: 9

Abstract

Purpose: The knowledge and understanding of risk management is critical in achieving project objectives in terms of time, cost, quality and safety. The study aimed at providing insight into how procurement methods could influence the effectiveness of risk management practices of housing projects in Akwa Ibom State. The objectives of the study were to evaluate the effectiveness of risk management methods of traditional, direct labour, and labour only procurement methods with a view to enhancing construction projects delivery in Akwa Ibom state and Nigeria in general. Design/methodology/approach: A cross-sectional survey approach was used for the study. Ninety-nine (99) questionnaires were retrieved from purposively selected contractors operating in the study area. Data collected were analysed using mean item score and Kruskal Wallis was used to test the hypotheses.Findings: The results indicate that Consulting with experts, past experience and brainstorming were the most moderate effective risk identification techniques employed by the respondents across the three procurement methods while risk analysis was rarely done. Risk response techniques shows 93.75% moderate effectiveness, with avoidance/prevention, transfer and mitigation were mostly employed, while risk retention was never used. Risk assessment was ineffective, while risk monitoring was of moderate effectiveness. Furthermore, the findings of the study revealed that there is no significant variation in the level of effectiveness of risk management methods among risk identification, response, monitoring among the delivery systems, but a significant variation in risk assessment. The study concluded that there is a general lack of knowledge of structured risk management practice by the respondents in housing projects.Research limitations/implications: The limitations include the use of only perception of contractors purposively selected from companies in Akwa Ibom state and only selected procurement methods. The contribution to knowledge is that this study has established the current level of effectiveness of risk management in some procurement methods in the study area.Practical implications: It is recommended that there is need for advanced formal and informal training in the characteristics and fundamentals of various procurement methods for adequate assessment of their inherent risks in the study area. There should be an iterative and systematic risk management approach that consider the specific risk factors and their assessment in the procurement practices.Originality/value: The study revealed the effectiveness level of sub processes of risk management among risk identification, assessment, response and monitoring, as well as the variation among the procurement methods. 

References

  1. Adenuga, O.A. (2013). Comparison of the performance of traditional and direct labour methods of project procurement: A case study of some selected projects of the Nigerian Army. Ethiopian Journal of Environmental Studies and Management, 6(1), 21-30.
  2. Agerberg, J. and Agren J. (2012), Risk Management in the Tendering Process: A Survey of Risk Management Practices within Infrastructural Construction. An unpublished M.Sc. Thesis in the Department of Technology Management and Economics Chalmers University of Technology, Sweden.
  3. Akinkumi, O. G., Aghimien, D. O. and Awodele, O.A. (2018). Appraising the use of Labour-Only Procurement System for Building Construction in Nigeria. Organization, Technology and Management in Construction. 10, 1719-1726.
  4. Akobi, G., (2012). The Comparison of Traditional and Direct Labour Procurement Methods Adopted by the Nigerian army. An M.Sc. thesis in the Department of Building, Faculty of Environmental Design, A. B. U. Zaria.
  5. Aladeniyi, B. (2013). Comparison of the Performance of Direct Labour and Labour Only Procurement Methods in Lagos State. An unpublished M.Sc. thesis in the Department of Building, University of Lagos.
  6. Alabi, A.O. (2018). Assessment of Risk involved in Housing Projects Procured Using Public Private Partnership System in Nigeria, International Journal of Economic, Commerce and Management, 6(12), 443-455.
  7. Babalola, O. D., Ibem, E. O., Olotuah, A. O. and Fulani, O. A. (2016), Residents' Perception of Quality of Public Housing in Lagos, Nigeria, International Journal of Applied Environmental Sciences, 11(2), 583-598.
  8. Babatunde, S. O., Opawole, A. and Ujaddughe, I. C. (2010). An Appraisal of Project Procurement Methods in the Nigerian Construction Industry. Civil Engineering Dimension. 12(1), 1-7.
  9. Banaitiene, N. and Banaitis, A. (2012). Risk Management in Construction projects (http://creativecommons.org/licenses/by3.0) http://dx.doi.org/10.5772/51460, accessed 23rd September, 2015.
  10. Chartered Institute of Building (CIOB) (2010), A Report on Exploring Procurement in the Construction Industry. Englemere, Kings Ride, Ascot Berkshire SL5 7TB, United Kingdom.
  11. Cooper, D., Grey B. Raymond., and Walker, P. (2005). Project Risk Management Guidelines: Managing Risk in Large Projects and Complex Procurements. Chiclester: John Wiley and Sons ltd.
  12. Davis, P. Love, P. Barccarini, D. (2008), Construction Innovation Report on Building Procurement Methods. Curtin university of Technology.
  13. Ejohwomu, O. A., Oshodi, O. S. and Onifade, M. K. (2016). Identifying the critical causes of conflict in construction projects in Nigeria, Nigerian Journal of Technology (NIJOTECH), 35 (2), 290 – 296.
  14. Ibeh, A.A., Adindu, C. C. and Oyoh, A. J. (2013). Public Private Partnership Construction Project Disputes in Nigeria. Journal of Research in National Development, 11(1), 6-11.
  15. James, E. E., Akpan, P. A., Essien, A. U. and Ekpo, K. J. (2012). The Pattern of Housing-Health Status among Residential Zones in Uyo Metropolis, Akwalbom State, Nigeria. Journal of Environmental Issues and Agriculture in Developing Countries, 4(3), 29-35.
  16. Kadiri, D. S. Ogunkola, O. M. (2014), Assessment of Procurement Methods Based on Clients Selection Criteria in Ogun State, Nigeria, Covenant Journal of Research in the Built Environment. 2(1), 31-41.
  17. Kajsa, S., (2006). Risk Management in Small construction projects; An Unpublished M.Sc. Thesis in the Department of Civil, Mining and Environmental Engineering, Luleå University of Technology, Sweden.
  18. Klemetti, A. (2006). Risk Management in Construction Project Networks. Helsinki University of Technology. Laboratory of Industrial Management Report. Available on http://www.tuta.hut.fi, accessed 20th December 2015.
  19. National Bureau of Statistics (NBS) (2015). Nigerian Construction Sector: Summary of Report 2010-2012.
  20. Odimabo, O. and Oduoza C.F. (2013). Risk Assessment Framework for Building Construction Projects in Developing countries, International Journal of Construction Engineering and Management, 2(5), 143-154.
  21. Ogunsami, E. (2013), Comparisons of Performance of Traditional and Labour Only Procurement in Construction Projects in Nigeria, DBA Africa Management Review, 3 (2), 1-15.
  22. Ogunsanmi, O. (2012), Comparison of Procurement Characteristics of Traditional and Labour-Only Procurement in Housing Projects in Nigeria, Civil and Environmental Research,2(8), 1-10.
  23. Ojo, O. S., Adeyemi, A. Y. and Fagbenle, O. I. (2006). The Performance of Traditional Contract Procurement on Housing Projects in Nigeria. Civil Engineering Dimension, 8(2), 81-86.
  24. Osipova, E. (2008). Risk management in construction projects: a comparative study of the different procurement options in Sweden, Unpublished Licentiate Thesis, Department of Civil, Mining and Environmental Engineering, Luleå University of Technology.
  25. Ozcan, G. (2008). A Generic Risk and Vulnerability Assessment Framework for International Construction Projects. An Unpublished M. Sc. Thesis in the Department of Civil Engineering Middle East Technical University.
  26. Perera, B. A. K. S., Rameeddeen, R. Chileshe, N. and Hosseinin, M. R. (2014). Enhancing the Effectiveness of Risk Management Practices in Sri Lankan Construction Projects: A Delphi Approach. International Journal of Construction Management, 14(1), 1-19.
  27. Project Management Institute (PMI) (2004), a Guide to the Project Management Body of Knowledge: PMBOK 3rd Edition, Pennsylvania: Project Management Institute.
  28. Ropel, M. and Gajewska, E. (2011). Risk Management Practices in a Construction Project –A Case Study, An M.Sc. Thesis in the Department of Civil and Environmental Engineering, Division of Construction Management. Chalmers University of Technology, Sweden.
  29. Sanda, Y. N., Anigbogu, N. A., Nuhu, Z. Y. and Olumide, O. S. (2020). A Life-Cycle Framework for Managing Risk in Public Private Partnership in Housing Project; Journal of Engineering, Project and Production Management. 10(1), 27-34.
  30. Serpella, A. F., Ferrada, X. Howard, R., Rubio, L. (2014). Risk Management in Construction Projects: A Knowledge– Based Approach. Journal of Social and Behavioural Sciences (119), 653-663.
  31. Udoh, N. (2014). The Determinants and Implications of Rural-Urban Migration in Nigeria. African Journal of Social Sciences, 4 (3), 133-143.
  32. Waziri, B. S. and Bala, K. (2014). Actualizing Nigeria's vision 20:2020 Imperatives of the Construction sector, Civil and Environmental research, 6 (6), 69-75.
How to Cite

Ujene, A. O., & Inyang, U. E. (2020). RISK MANAGEMENT EFFECTIVENESS IN HOUSING PROJECTS: A COMPARATIVE EVALUATION IN SELECTED PROCUREMENT METHODS IN AKWA IBOM STATE. Journal of Contemporary Research in the Built Environment, 4(1), 36-54. https://doi.org/10.68128/jocrebe.2022.vjx0g6qi

A. O. Ujene, and U. E. Inyang, "RISK MANAGEMENT EFFECTIVENESS IN HOUSING PROJECTS: A COMPARATIVE EVALUATION IN SELECTED PROCUREMENT METHODS IN AKWA IBOM STATE," Journal of Contemporary Research in the Built Environment, vol. 4, no. 1, pp. 36-54, March 2020. doi: 10.68128/jocrebe.2022.vjx0g6qi

Share this article:
Facebook X / Twitter LinkedIn