Research Article

STAKEHOLDERS’ PERCEPTION OF THE CAUSES AND EFFECTS OF VARIATION ORDERS IN PUBLIC CONSTRUCTION PROJECTS IN SOUTH-SOUTH ZONE OF NIGERIA

1 Department of Quantity Surveying, University of Uyo, Uyo, Akwa Ibom State, Nigeria
2 Department of Quantity Surveying, College of Engineering and Environmental Sciences, Bells University of Technology, Ota, Nigeria
* Corresponding author: teatea4t@yahoo.com
Published: Mar, 2019
Pages: 44-58
Views: 24
Downloads: 6

Abstract

Purpose: The construction process is a complex and risky endeavour often associated with unexpected changes which can occur at any stage of the project and may eventually lead to issuance of variation orders. Variation orders are subject to numerous factors which have significant effects on project performance. The study examines the causes and effects of variation orders in construction projects within the South-South geopolitical zone of Nigeria. The choice of the study area is determined by its socio-economic importance to the nation. Design/methodology/approach: The study adopts the exploratory survey design approach in order to obtain the perception of professionals in the building construction industry on the causes and effects of variation order on construction projects. 241 valid questionnaires were used giving a response rate of 62.27%. Data obtained are analysed using mean score method, and Kruskal Wallis tests. Findings: The findings reveal that change of scope of work, errors and omissions in design, change in specifications by client, client`s financial difficulties and inadequate project objectives were the dominant causes of variation orders. In addition, the major effects of variation orders include the increase in overall project duration, increase in project cost, disputes, schedule delays, and rework. The conclusion is that, there is no difference in the perception of clients, consultants and contractors concerning the causes and effects of variation orders on the performance of construction projects. Practical implication: Professionals in the building construction industry should find the results of this research useful in enhancing their knowledge on effective project delivery and understanding the nature of causes and effects of variation order. Originality/value: Findings reveal that all the key stakeholders in the building construction industry; clients, consultants and contractors exhibit similar perceptions of the causes and effects of variation order in construction project delivery. This attests to the fact that variation is inevitable in construction projects.

References

  1. Alaryan, A., Emadelbeltagi., Elshahat, A. and Dawood, M. (2014). Causes and effects of change orders on construction projects in Kuwait. International Journal of Engineering Research and Applications (IJERA), 4(7), 01-08.
  2. Alnuami, S A., Ramzi, A.T., Mohammed, M. and Ali, S. A. (2010). Causes, effects, benefits and remedies of change order on public construction project in Oman. Journal of Construction Engineering and Management, 136(5), 615-622.
  3. Alsuliman, J., Bowles, G. and Chen, Z. (2012). Current practice of variation order management in the Saudi construction industry. Association of Researchers in Construction Management, 1-10.
  4. Arain, F.M., Assaf, S. A. and Low, S.P. (2004). Causes of discrepancies between design and construction: Contemporary issues and sustainable practices in the built environment. Architectural Science Review, 47(3), 237-249.
  5. Arain, F. M. and Low, S. P. (2005). The potential effects of variation orders on Institutional building projects facilities. Accessed on 23rd of Nov. 2012, 496–510. Doi:10.1108/02632770510618462.
  6. Arain, F.M. and Pheng, L.S. (2005). How design consultants perceive causes of variation orders for institutional buildings in Singapore. Architectural Engineering and Design Management, 1(3), 181-196.
  7. Awad, M. (2001). Analysis and management of change orders for combined sewer flow construction projects. Unpublished Dissertation, Wayne State University.
  8. Charoenngam, C., Coquinco, S.T. and Hadikusumo, B.H.W. (2003). Web-Based Application for Managing Change Orders in Construction Projects, Construction Innovation, 3, 197-215
  9. Cheng, M.Y. Tsai, H.C., and Sudjono, E. (2011). Evaluating subcontractors' performance using evolutionary fuzzy hybrid neural network. International Journal of Project Management. 29, 249-356.
  10. Construction Industry Institute (CII). (1990). Scope definition and control, Publication 6–2, CII, University of Texas at Austin, Austin, Texas.
  11. Cunningham, T. (2013). Factors affecting the cost of building work - An overview. Retrieved September 8, 2016 from arrow.dit.ie/cgi/viewcontent.cgi?article=1028&context=beschreoth.
  12. Desai, J. N., Pitroda., J and Bhavasar, J. J. (2015). Analysis of factor affecting change order in construction industry using RII method. International Journal of Modern Trends in Engineering and Research (IJMTER), 2(6), 2349–9745.
  13. Enshassi, A., Arain, F. and Al-Raee, S. (2010). Causes of variation orders in construction projects in the Gaza Strip. Journal of Civil Engineering and Management, 16(4), 540-551.
  14. Fisk. E. R. (1997). Construction Project Administration, 5th edition.
  15. Fisk, E. R. and Reynolds, W. (2005). Construction Project Administration (8th Edition) Edition ministration (8th Edition), ISBN-13: 978-0130993052.
  16. Geok, O. S. (2002). Causes and improvement for quality problems in design and build projects. Unpublished B.Sc. Thesis, National University of Singapore. Singapore.
  17. Gokularkrhi, M. and Gowrishankar, K.S. (2015). A study on impacts of change order in construction projects. International Journal of Science and Engineering Research (IJOSER), 3(4), 3221.
  18. Halwatura R.U. and Ranasinghe, N. P. (2013). Causes of variation orders in road construction projects in Sri Lanka, Hindawi Publishing Corporation, ISRN Construction Engineering.
  19. Hanna, A., Calmic, R., Peterson, P.A. and Nordheim, E.V. (2002). Quantitative definition of projects impacted by change orders. Journal of Construction Engineering and Management, 128(1), 57-64.
  20. Harbans, S.K.S. (2003). Valuation of varied work: A commentary. In: Bulletin Ingénieur, The Board of Engineers Malaysia, 20(3), 32-42.
  21. Homaid, N., Eldosouky, A. and AlGhmdi, M. (2011). Change orders in Saudi linear construction projects. Emirates Journal for Engineering Research, 16(1), 33-42.
  22. Ibbs, C. W. (1997). Quantitative impacts of project change: Size Issues. Journal of Construction Engineering and Management, 123(3), 308-311.
  23. Ijaola, I.A. and Iyagba R.O. (2012). A Comparative study of causes of change orders in public construction project in Nigeria and Oman, (JETEMS), 3(5), 495-5012.
  24. Jadhav, O. U. and Bhirud, A. N. (2015). An analysis of causes and effects of change orders on construction projects in Pune. International Journal of Engineering Research and General Science, (3)6.
  25. Joint Legislative Audit and Review Commission (JLARC) (2001). Review of construction costs and time schedules for Virginia highway projects. Retrieved from: http://jlarc.virginia.gov/reports/Rpt258.pdf.
  26. Kazaz, A., Manisali, E. and Ulubeyli, S. (2008). Effect of basic motivational factors on construction workforce productivity in Turkey. Journal of Civil Engineering and Management, 14(2), 95-106.
  27. Keane, P., Sertyesilisik, B. and Ross, A. (2010). Variations and change orders on construction projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 2(2), 89-96.
  28. Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23, 285-294.
  29. Lokhande, M. A. and Ahmed, F. S. Y. (2015). Assessing consequences of change order request impact in construction industry of Yemen: An explorative likert-scale based survey design. Management, 5(5), 141-147.
  30. Lo, T., Fung, I. and Tung, K. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636–649.
  31. Memon, A. H. Rahman, I. A. and Memon, A. H. (2014). Assessing the occurrence and significance of variation order factors in affecting quality of construction projects. Life Science Journal, 11(7), 247-253.
  32. Memon, A. H., Rahman, I. A. and Hussan, M. F. A. (2014). Significant causes and effects of variation orders in construction projects. Research Journal of Applied Sciences, Engineering and Technology, 7(21), 4494-4502.
  33. Mohamed, A.A. (2001). Analysis and management of change orders for combined Sewer over flow construction projects', Dissertation, Wayne State University.
  34. Mohammad, N., Che, A. A., Rakmat, R.A.O.K. and Yusof, M. (2010). Investigation on the causes of variation orders in the construction of building project - a study in the State of Selangor, Malaysia. Journal of Building Performance, 1(1), 73-82.
  35. Msallam, M., Abojaradeh, M., Jrew, B. and Zaki, I. (2015). Controlling of variation orders in highway projects in Jordan. Journal of Engineering and Architecture, 3(2), 95-104.
  36. Ngwepe, L., Aigbavboa, C. and Thwala, W (2015). The critical determinants of variation orders on SA Public Sector Construction Projects.
  37. O'Brien, J. J. (1998). Construction change orders. McGraw Hill, New York. Contemporary Issues and Sustainable Practices in the Built Environment.
  38. Odediran, S.J. and Windapo, A.O. (2014). Systematic review of factors influencing the cost performance of building projects In: Laryea, S. and Ibem, E. (Eds) Proceedings 8th Construction Industry Development Board (cidb) Postgraduate Conference, 10-11 February 2014, University of the Witwatersrand, Johannesburg, South Africa, 501-520.
  39. Osman, Z., Omran, A. and Foo, C. K. (2009). The potential effects of variation orders in construction projects. Journal of Engineering, 2, 141–152.
  40. Ssegawa, J.K., Mfolwe, K.M., Makube, B. and Kutua, B. (2002). Construction variations: A scourge or a necessity? Proceedings of the First International Conference of CIB W107, 11-13 Nov. 2002, Cape Town, South Africa, pp 87-96.
  41. Sunday, O. A. (2010). Impact of variation orders on public construction projects. In: Egbu, C. (Ed) Procs 26th Annual ARCOM Conference,6-8 September 2010, Leeds, UK, Association of Researchers in Construction Management, 101-110.
  42. Tadesse, A. (2009). Causes and effects of variations in Ethiopian federal road projects, MSc. Thesis, Addis Ababa University School of civil and Environmental Engineering, Ethiopia.
  43. Udofia, E.P. (2011). Applied Statistics with Multivariate Methods. Enugu, Nigeria: Immaculate Publications Limited, 218.
  44. Yadeta, A. E. (2016). Causes of variation orders on public building projects in Addis Ababa. International Journal of Engineering Research and General Science, 4(4).
  45. Yaman, H. (2007). A building cost estimation model based on functional elements. Publication of Istanbul technical University, A/2(4), 73-87.
  46. Zaneldin, E.K. (2006). Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5), 453-459.
  47. Zawawi, N., Azman, N. and Kamar, M. (2010). Sustainable Construction Practice: A review of Change Orders in Construction Projects. International Conference on Environment, 13-15 Dec., Pulau Pinang.
How to Cite

Adu, E. T., Sanni, A. O., & Asuquo, C. F. (2019). STAKEHOLDERS’ PERCEPTION OF THE CAUSES AND EFFECTS OF VARIATION ORDERS IN PUBLIC CONSTRUCTION PROJECTS IN SOUTH-SOUTH ZONE OF NIGERIA. Journal of Contemporary Research in the Built Environment, 3(1), 44-58. https://doi.org/10.68128/jocrebe.2019.00orood8

E. T. Adu, A. O. Sanni, and C. F. Asuquo, "STAKEHOLDERS’ PERCEPTION OF THE CAUSES AND EFFECTS OF VARIATION ORDERS IN PUBLIC CONSTRUCTION PROJECTS IN SOUTH-SOUTH ZONE OF NIGERIA," Journal of Contemporary Research in the Built Environment, vol. 3, no. 1, pp. 44-58, March 2019. doi: 10.68128/jocrebe.2019.00orood8