TIMELY DELIVERY OF PROJECTS AND ECONOMIC DEVELOPMENT IN NIGERIAN CONSTRUCTION INDUSTRY: A CASE STUDY OF ONDO STATE
1 Department of Quantity Surveying, Federal University of Technology, Akure, Ondo State
* Corresponding author: olusolaolatunji89@gmail.com
* Corresponding author: olusolaolatunji89@gmail.com
Abstract
Purpose: The relationship between timely delivery of construction projects success and
economic development in Nigerian construction industry involves managing the resources—
workers, machines, money, materials and methods used. Some projects are effectively and
efficiently managed while others are mismanaged, incurring much delay and cost overruns and
negatively affecting the economy. This paper assessed the relationship between timely delivery
of construction projects and economic development in Nigerian construction industry.
Design/methodology/approach: Survey design was adopted to collect data from professionals
from the study area. Questionnaires were administered to construction professionals in Ondo
state which include Architects, Builders and Quantity Surveyors. The quantitative research
method was adopted for this study and the adopted questionnaire was structured on a five-point
Likert scale to elicit the opinion of respondents on timely delivery of projects and economic
development in the Industry. Spearman correlation coefficient was used for assessing the
relationship between timely delivery of construction projects and economic development.
Findings: It was evident from the study that there is slightly high relationship between timely
delivery of construction projects and economic development within Nigerian construction
industry with the highest degree being 55.1% and lowest as 31%. The findings revealed that
timely delivery of construction projects tends to increase economic growth in the study area.
Originality/value: This study recommends that there should be proper planning of a project
before the commencement of the construction so every activity can go smoothly and the project
can be delivered on time. Likewise, contractors should be familiar with the site of the
construction so they can have knowledge of the topography so there would not be problem of
unforeseen ground conditions.
Keywords
Construction industry; economic development; infrastructure; project success.
How to Cite
Olatunji, S. O., Arowoiya, V. A., & Omolewa, O. O. O. (2019). TIMELY DELIVERY OF PROJECTS AND ECONOMIC DEVELOPMENT IN NIGERIAN CONSTRUCTION INDUSTRY: A CASE STUDY OF ONDO STATE. Journal of Contemporary Research in the Built Environment, 3(2), 92-100. https://doi.org/10.68128/jocrebe.2019.vpf4zft8
S. O. Olatunji, V. A. Arowoiya, and O. O. O. Omolewa, "TIMELY DELIVERY OF PROJECTS AND ECONOMIC DEVELOPMENT IN NIGERIAN CONSTRUCTION INDUSTRY: A CASE STUDY OF ONDO STATE," Journal of Contemporary Research in the Built Environment, vol. 3, no. 2, pp. 92-100, September 2019. doi: 10.68128/jocrebe.2019.vpf4zft8